Project Management

David Huard edited this page Oct 29, 2019 · 30 revisions

The full list of project deliverables are listed in the Canarie 2B Project page. Most of the issues stem from the raven repository, but some are tied to other PAVICS and birdhouse related repositories.

Progress is tracked using the Canarie 2B Project using a chrome extension computing story points. The idea is to write in each issue title the number of total story points and the number of spent points completed. So for an example, an issue could be Write documentation (4), which would mean that completing the story requires 4 story points. The extension will sum for each column the total points.

Conventions

  • One story point corresponds to roughly one day of work +/- 4 hours.
  • Choose story points from the sequence: 1, 2, 4, 8. If the story is bigger than 8, split it in individual smaller issues.
  • An issue is complete only when it is in the Done column. This means it has been deployed and shown to work.
  • Relative progress will be estimated as the fraction of points in the Done column plus half of the points in the Deploy and Verify columns over the total number of points.
  • I suggest we assume linear progress over the year, that is 11.5% each 6 weeks.

Story points

Date Backlog To do In progress Verify Deploy Done Total % Complete % Expected
2018-06-12 202 0 0 0 0 0 202 0 0
2018-08-14 158 28 13 3 0 6 208 4 11
2018-09-25 138 22 39 7 0 6 212 5 22
2018-11-06 112 30 31 8 26 9 216 12 33
2018-12-13 92 16 41 20 4 43 216 25 44
2019-01-28 84 12 37 26 8 49 216 31 55
2019-03-12 40 40 27 42 0 67 216 41 67
2019-04-22 28 28 19 32 0 109 216 58 78
2019-06-04 32 1 16 36 0 120 205 67 89
2019-06-20 36 0 12 26 0 130 204 70 93
2019-09-17 28 4 8 0 0 164 204 80 100
2019-10-29 28 4 4 0 4 164 204 81 100